Construction works for “450 MW + 200 Gcal Navoi-2 Electric and Heat Power Plant Project" initiated by Çalık Enerji in Navoi, Uzbekistan continues at full steam.
There are two thousand one hundred and eighty personnel working for the Navoi-2 Project as part of Çalık Enerji, Mitsubishi Hitachi Power Systems (MHPS) and Mitsubishi Corporation.
Project's overall progress rate is currently 68,99%. Start-up process for BOP systems has been initiated and it is planned to start the gas turbine and generator as a simple cycle and begin power generation at the beginning of 2019.