Çalık Enerji
News
ST & STG-1 (steam turbine & generator) on-base installation works have been completed in 29 November 2018 and ST & STG-2 (steam turbine & generator) on-base installation works have been completed in 23 December 2018 as part of the project. Current percentage of completion of the project is 62,40 % and contractual delivery date of the project is April 2020.