We, as Çalık Enerji, are among the leading global energy companies with many successful turn-key contracting projects around the world, since the inception of our company in 1998.
We, as Çalık Enerji, are among the leading global energy companies with many successful turn-key contracting projects around the world, since the inception of our company in 1998.
We supplied and mounted all ancillary equipment in addition to all main equipment required for operation of the power plant and delivered it to the employer as a Turnkey project.
EPC contract includes all conceptual and detailed design, procurement of equipment, construction, and mounting of all mechanical, electricity, instrumental and control systems for the Power Plant. The contract also comprises operation tests, commissioning and training of employer's staff.
Project Title : Balkanabat-2 Simple Cycle Power Plant
Capacity : 254,2 MW
Equipment : Simple Cycle, 2xGE-PG9161-E (Frame 9E)
Voltage Level : 110 kV
Commencement Date : July 2008
Date of Delivery : April 2010
Employer : Ministry of Energy, Turkmenistan