We, as Çalık Enerji, are among the leading global energy companies with many successful turn-key contracting projects around the world, since the inception of our company in 1998.
We, as Çalık Enerji, are among the leading global energy companies with many successful turn-key contracting projects around the world, since the inception of our company in 1998.
We supplied and mounted all ancillary equipment in addition to all main equipment required for operation of the power plant and delivered it to the employer as a Turnkey project.
EPC contract includes all conceptual and detailed design, procurement of equipment, construction, and mounting of all mechanical, electricity, instrumental and control systems for the Power Plant. The contract also comprises operation tests, commissioning and training of employer's staff.
Project Title : Derweze Simple Cycle Power Plant
Capacity : 504,4 MW
Equipment : 4 x GE PG9171-B (Frame 9E)
Voltage Level : 110 kV / 220 kV
Commencement Date : July 2013
Date of Delivery : September 2015
Employer : Ministry of Energy, Turkmenistan
Scope : Lump Sum Turnkey EPC Prime Contractor