We, as Çalık Enerji, are among the leading global energy companies with many successful turn-key contracting projects around the world, since the inception of our company in 1998.
We, as Çalık Enerji, are among the leading global energy companies with many successful turn-key contracting projects around the world, since the inception of our company in 1998.
The power plant with total installed capacity of 149,2 MW is composed of 3 pieces of about 50 MW GE-LM 6000 gas turbines. LM 6000 turbines are designed in a way to generate power in full capacity only within 10 minutes. The turbines are also important for Çalık Enerji as they will be the first of their kind in Turkmenistan and constructed by Çalık Enerji.
In addition, Çalık Enerji took over turnkey construction and mounting of all main and ancillary equipment required for operation of the power plant.
EPC contract includes all conceptual and detailed design, procurement of equipment, construction, and mounting of all mechanical, electricity, instrumental and control systems for the power plant. The contract also comprises operation tests, commissioning and training of employer's staff.
Upon the completion, the project was delivered to Turkmenistan Ministry of Energy for operation.
Project Title: Lebap Simple Cycle Power Plant
Capacity : 149,2 MW
Equipment : 3 x GE LM6000
Voltage Level : 110 kV
Commencement Date : May 2013
Date of Delivery : February 2014
Employer : Ministry of Energy, Turkmenistan
Scope : Lump Sum Turnkey EPC Prime Contractor